top of page

TRANSPORTATION

Highway I-94: Dan Ryan

Client IDOT representative Resident Engineer construction management team.

​

First designed and built in the early 1960’s, the Dan Ryan Expressway is the busiest expressway in the Chicago area. Accommodating over 300,000 vehicles per day, it is the city's major transportation artery from downtown through the city's South Side. Walsh Construction was awarded a series of contracts totaling more than $500M to reconstruct the Expressway. Work began in the summer of 2003 with the reconstruction of bridges and ramps. Damaged retaining walls were reinforced, and key frontage roads were reconstructed. During construction, Northbound and Southbound express lanes were closed for four miles and Walsh Construction crews began working around the clock to replace them. Work includes the removal and replacement of over 400,000 square yards of concrete pavement. Also included is the construction of sewers and drainage systems, new concrete barrier walls, signage, and landscaping. Walsh is fully responsible for developing and implementing the traffic control use.

Location:

Chicago, Illinois

 

Owner:

Illinois Department of Transportation

 

Architect:

Various

 

Project Value:

$170M

 

Completion Date:

November 2007

 

Project Website:

Dan Ryan Expressway 

Wacker Drive Reconstruction

Client CDOT representative NASH CEO part of Construction Management team:

​

Walsh Construction led the historic effort to "Revive Wacker Drive", downtown Chicago's historic two-tier roadway used by over 60,000 vehicles a day. Walsh complete three separate contracts for a total value of $184 Million on Wacker Drive, and completed the project early. Work consisted of the complete demolition and replacement of the viaduct, lower Wacker roadway, and historical architecture including the 8 adjacent cross streets and structures for a total of 4400 LF of roadway. The two-mile-long roadway carries tens of thousands of vehicles to the Loop. Eight bascule bridges intersect the upper roadways and two elevated transit lines. This project was a Midwest Construction Top Illinois Project of 2002.

Location:

Chicago, Illinois

 

Owner:

Chicago Department of Transportation  

 

Architect:

Alfred Benesch & Company & AECOM Company  

 

Project Value:

$184M

​

Completion Date:

November 2002 

Millennium Park

Client Public Building Commission of Chicago Representative NASH CEO part of Construction management team:

 

This project included four phases of work, each awarded as a separate package to Walsh Construction. The first contract included trellis & messenger cable systems and steel trellis structure and support systems, as well as electrical work to accommodate audio system in and under trellis. Work also included the support steel for metal elements and the straight segmented structural steel dia-grid system for support of stainless steel cladding system as well as the installation of that system. That installation included the development & completion of conceptual design. The second portion called for performance work on the Pavilion (General Work). landscaping segment and ice rink contract were also awarded to Walsh.

​

​

Project Value:

$203M

 

Owner: 

Public Building Commission of Chicago 

bottom of page